THE CONSTRUCTION PROJECT: Do we have a team? Part II
Real Estate Real Estate Other Business Contract Real Estate Construction
Summary: What are we building and what’s the real price? Fundamental to a construction agreement are two seemingly basic and simple concepts: the scope of work and the total project price. Yet they are a frequent source of dispute and litigation.
What are we building and what’s the real price?
Fundamental to a construction agreement are two seemingly
basic and simple concepts: the scope of
work and the total project price. Yet
they are a frequent source of dispute and litigation. Common problems are:
1.
The
construction drawings lack sufficient detail which leads to different
interpretations between the subcontractor and contractor, and potentially to price
disputes between the owner and contractor.
2.
The plans, specifications, shop drawings and
related documents, which together constitute the owner’s vision, are incomplete
at the time the construction agreement is signed; or are inconsistent with one
another.
3.
What the owner understands as a fixed price is
really cost-plus, because there are many “allowances” which budget a lower
priced material or level of craftsmanship than what the owner envisions.
4.
The cost-plus agreement includes contractor
charges that are characterized as “cost”, but sure look like another contractor
profit center.
To achieve team objectives everyone must…
1.
The collaborative efforts of the owner and
design professionals produce drawings and specifications which both capture the
owner’s vision and leave virtually no aspect of the construction project design
unclear or incomplete. And this needs to
be accomplished and delivered to the contractor as part of the bid process. In order to achieve this, the owner must
spend the necessary time and money with the design professionals to make
certain that all design documents are complete and accurate.
2.
The contractor receives a complete package from
the owner and design professionals (including the interior designer and
landscape architect, if applicable) and bids the job with as few allowances as
possible. Where there are allowances,
the contractor ensures that the owner understands fully, what assumptions have
been employed when determining the budget for an allowance. The key here is
that the owner and contractor must be realistic with one another. An allowance
should not be viewed by either party as a future negotiation event. The contractor must provide the owner with a
detailed list of what has been selected by the contractor for the category for
which an allowance is given (for example how do you know the flooring, cabinet or
landscaping allowance is sufficient without reviewing the actual tile or wood
samples; cabinet doors; and a list of specific trees and scrubs and their
quantities?). The owner must not turn a
blind eye and think somehow an insufficient allowance will improve with age.
3.
In a cost-plus contract the owner and contractor
define clearly all payments which will be made to the contractor for anything that
is not allocable to a subcontractor. In other words, when the contractor
characterizes an item as “cost” which is in fact overhead reimbursement for the
contractor’s corporate overhead (not job site overhead) and moreover, in some
cases not actual costs but instead an item the contractor estimates as overhead - - - does the owner understand what the
contractor is doing and after full disclosure approves of the concept? Does the owner agree that the business deal
includes these payments? There are many
good and legitimate reasons why a contractor should be paid for corporate
overhead and other items. Further, a
cost-plus agreement with site and corporate overhead also charged as an item of
“cost”, can still save the owner significant sums versus a fixed-price
contract. The key is full disclosure and
a meeting of the minds at the beginning of the job.
Only when the owner, contractor,
and design professionals have a clear and identical understanding of “what are
we building?” and “what’s the real
price?” can the construction team achieve team objectives.